600 |
How can include the values in the inner cells in the drop down filter window
With Gantt1 .DrawGridLines = exRowLines .VisualAppearance.Add 1,"c:\exontrol\images\normal.ebn" .Description(exFilterBarBlanks) = "" .Description(exFilterBarNonBlanks) = "" With .Columns.Add("Single Column") .HTMLCaption = "Single column with <b>inner cells</b>" .ToolTip = "Click the drop down filter button, and the filter list includes the inner cells values too." .DisplayFilterButton = True .DisplayFilterPattern = False .FilterList = exIncludeInnerCells End With .ShowFocusRect = False With .Items s = .SplitCell(.AddItem("S 1.1"),0) .CellCaption(,s) = "S 1.2" .CellHAlignment(,s) = CenterAlignment .CellBackColor(,s) = &H1000000 .CellWidth(,s) = 84 s = .SplitCell(.AddItem("S 2.1"),0) .CellCaption(,s) = "S 2.2" .CellHAlignment(,s) = CenterAlignment .CellWidth(,s) = 84 s = .SplitCell(.AddItem("S 3.1"),0) .CellCaption(,s) = "S 3.2" .CellHAlignment(,s) = CenterAlignment .CellBackColor(,s) = &H1000000 .CellWidth(,s) = 84 End With End With |
599 |
How can I sort the value gets listed in the drop down filter window
With Gantt1 .LinesAtRoot = exLinesAtRoot .MarkSearchColumn = False .Description(exFilterBarAll) = "" .Description(exFilterBarBlanks) = "" .Description(exFilterBarNonBlanks) = "" With .Columns.Add("P1") .DisplayFilterButton = True .DisplayFilterPattern = False .FilterList = exSortItemsDesc End With With .Columns.Add("P2") .DisplayFilterButton = True .DisplayFilterPattern = False .FilterList = exSortItemsAsc End With With .Items h = .AddItem("Z3") .CellCaption(h,1) = "C" .CellCaption(.InsertItem(h,,"Z1"),1) = "B" .CellCaption(.InsertItem(h,,"Z2"),1) = "A" .ExpandItem(h) = True End With End With |
598 |
Is there a way to break the hours into 15 minute increments just showing lines instead of the minute numbers
With Gantt1 .BeginUpdate .Chart.FirstVisibleDate = #2/5/2008# .Chart.LevelCount = 3 .Chart.Level(0).Label = "<b><%mmm%> <%dd%></b> <%yyyy%> " With .Chart.Level(1) .Label = "<%hh%>" .Alignment = CenterAlignment End With With .Chart.Level(2) .Label = "" .Unit = exMinute .Count = 15 End With .Chart.UnitWidth = 6 .EndUpdate End With |
597 |
How can I change the visual appearance of the milestone bar using EBN
With Gantt1 With .VisualAppearance .Add 1,"gBFLBCJwBAEHhEJAEGg4BKMMQAAYAQGKIYBkAKBQAGaAoDDMMILQiMQwjRBMKgBBCLIxiGK4DhiF4aRTHUKAAKQahLEaSZLhEZRQiqA4sS5FQBSBDQFwSByEY6mSaYJ" & _ "AWK4tCyNM7SfQAbxnAgYaLAAYRUjuHZOTZAc4UfAdFL/K4AKrfeZIeAiCRQGiYZyHKaRShjDwXKLIIjbJhkNoJChCNQgBScPgxCx8JypaCaar2fjQM6zWAMdb2Cz7PjD" & _ "H7wPA1WYJRaDYjhcB4LheAqGXBWUYLYb8XS3EKJYhiWA4HjqFjGJpcEzPbRiNx3H6SABlLLaLo7JpGO52FrTHZjXyzLqBVpoOyEbrmcozYzjN41RpWETfQYDcwteqcLp" & _ "rhGVZrm6dp8j4bAnDQP5Uh+OpcH6R4Lg2YJvEIeg6kWEoJB2ZZyG6GoLCSXxtG+IZ1GmfhJjcawNFWfB/h+V5pnUc5VhWeZ4BMX4jlySwtiAJodlEYRaBYFgHHgIA2gG" & _ "ExkFUdxFl6A5hgUbgXgcVRzFiXA3CICARAEgI" .Add 2,"CP:1 -6 0 5 0" End With With .Chart .FirstVisibleDate = #1/1/2001# With .Bars.Add("MilestoneEBN") .Color = &H2000000 .Height = 14 End With End With .Columns.Add "Tasks" With .Items .AddBar .AddItem("Milestone"),"Milestone",#1/2/2001#,#1/2/2001 0:00:01 AM# .AddBar .AddItem("Milestone EBN "),"MilestoneEBN",#1/2/2001#,#1/2/2001 0:00:01 AM# End With End With |
596 |
How can I change the visual appearance of the summary bar using EBN
With Gantt1 .VisualAppearance.Add 1,"gBFLBCJwBAEHhEJAEGg4BGICg6AADACAxRDAMgBQKAAzQFAYZhhBaERiGEaIJhUAIIRZGMQxXAcMQvDSKQJhGDAADEMgyAJCIxjPIgZBoGqPBpASQJUhkMocR7HMygB" & _ "IkSRNA8kMwxdQEaw9ECRIDpGaYWTFDhsABTVQRLL0Tw9ISERqoSSaGgkCYaA7CNJ0PBNJSjJ6LJZGURbKqyCQ1DBbUB3BaUaQ9JaKa7pKa7cpWKIqSxEMrxcLFcT5DSb" & _ "YDxGjLEhmPZBVZQNBxtJbFQHWJCNgzVAdOAAfzQM70GpMQoWJYeVpEObSBD1dABTCBczADYoex7ID+aJuGiYVZdWxJOjfbhkTTIJAaCawABrWxR8iHN5paTnUpzDjwbg" & _ "0kqRRyr+XwjA8Go/HSBp6g6KJTFcGpWmYdg8H6dJTH0EZelueBfBuLwyBMd50nIfR+kmXB4BECQUAaEYMHQHRHCGFRYI2ZAwEIExghQZA2EIQoGGoEhOgGBBYlAeYYHM" & _ "WJcDcGx4HYHoHmICIFjeBohkaDAAC2DAjBYJIIiKSI2CSC5hjQJBsCOCwYiIKoGmKWJkn6DANkiWgzCwYwolAcQkksWJaCuDohlicg2hDQR+EELBInKcJohMJBomILoG" & _ "mISQuESFBOgkOQDg+SoTEyfoXCUSImDyGZhjkaI1hcJgTnoXgACYCYKG2GQkEkVJchKIoZDIbIciYKY+HEP4mlmThSg+aBIlKBYUCUKgGHyG4jEkPoKiAKI6D6EokGkS" & _ "gyECF5jEKVJZD+aYqHKG4nGoCh+iKJ4qEqBokh+KYag6JoqmqKo2iWJpqgKRJHDiT5qk6NYtCsapmjiLprHqdo6i8awan6QovCwOp6kSLQsBsHpGjKbBbBaMYhm0Cgal" & _ "ILBtBsUpTiGUIUAQgIA==" With .Chart .FirstVisibleDate = #1/1/2001# With .Bars.Copy("Task","Summary") .Color = &H1000000 .Height = 16 End With End With .Columns.Add "Tasks" With .Items .AddBar .AddItem("Task 1"),"Task",#1/2/2001#,#1/4/2001# .AddBar .AddItem("Task 2"),"Summary",#1/5/2001#,#1/7/2001# End With End With |
595 |
How can I change the visual appearance of the task bar using EBN
With Gantt1 .VisualAppearance.Add 1,"gBFLBCJwBAEHhEJAEGg4BGoCg6AADACAxRDAMgBQKAAzQFAYZhhBaERiGEaIJhUAIIRZGMQxXAcMQvDSKQJhGLhQiSJoJDSBEgSXDIZQ5D6OZYACDJQACJYJTbAYzyP" & _ "JkPRAA6EZCmGAwCglf5HABRb7xNLkbQ8GySKJnWCQJhoD5BSLCNRUTRFFQtGgZBpEWwLCjQNQwWLKFoTJIEPSBDKqYDoKYqTgOOZOThHQz3HakQRdAa/ZpnaKpUo2d47" & _ "XjMWBwGA0EzeAAGaxoShqdoiFaGU7UOJVJBOGwHK6BchoMAKbp6XoVWRaOAWLZWVABM7XLZxbLccyGfZ1XhdV5UbqUMznR7PNrjLKIJpCOJbbyAFwgBaeQABYLhK7iHR" & _ "mi8XYwjMWpjFWOx1GIB5LmgdB4HCEBECSIBpDGHQOicIwokYPImikEIJj6eJIloEgogSc40FGcJEFiYZIG2VIoAURw1g2QxyAQNwNAMPJOgIYI4CoDIBmAeAKBIUpQDU" & _ "KJYDoTpIB4vxgmgdgNgeYZDDoFw7CEJhQn+BohmKfImCWSZRlgYwikYMQ0gwF4DniTA/gwBJYjQYwsgoIg6AyCRQDiIJODAZBImoOguAmMZ4lQLIJjOMI3CYZJpEIT4K" & _ "iKSI6DqD5ZGAAgHC2DAjBYR4SGUGYGE+GIlCmFhRhIB5iFAbwWsiJgMhoCoxngV4ZCcSYOHaGYnHmIg8COJpoCoOISmSWZeHWHgoEkRoAg4EIYB4NogmiSgKg6GRjGoJ" & _ "gFh+ZJKDaBYjmgaQygiBRUHmbhoDsTAyiqIIoioGoOw8aoKhKKoemeOIaAeF5HmqHoqiyKxKgYaN/locgBiuZRojoVIok8cwsjaMBLGqDoAhGIpoEYWYEmAIxUkQLZmg" & _ "iYg2g2I4JiCQwuAqWIOIkEAQICA==" With .Chart .FirstVisibleDate = #1/1/2001# With .Bars.Item("Task") .Color = &H1000000 .Height = 16 End With End With .Columns.Add "Tasks" With .Items .AddBar .AddItem("Task 1"),"Task",#1/2/2001#,#1/4/2001# .AddBar .AddItem("Task 2"),"Task",#1/5/2001#,#1/7/2001# End With End With |
594 |
How can I change the visual appearance of the task bar using EBN
With Gantt1 .VisualAppearance.Add 1,"gBFLBCJwBAEHhEJAEGg4BZsIQAAYAQGKIYBkAKBQAGaAoDDMMILQiMQwjRBMKgBBCLIxiGK4DhiGoZATCMbDBIcSwSGgCJCjeS4ZDKHIXSxFUKTBAcSQTGyBRokaYZR" & _ "i6A4+TRPETTWAEcABHSbQCoKTKAoCHpLQLMYxDKItJSpGYaRgqWCaZpuUIaUzKVbxbK9CSMGiQbIsOJrBqqQozWZHVITLR9VgBNqga7uGR5DoqdovU5dVTVda9Ly5LSs" & _ "MQvfALCqOe45URdNp3RiVBYfI6+cZvfJLWh4NqeAbCMC1UJoYhlUKCBg0TRoVo9AIDX5QWaYXC0AkBA==" With .Chart .FirstVisibleDate = #1/1/2001# With .Bars.Item("Task") .Color = &H1000000 .Height = 16 End With End With .Columns.Add "Tasks" With .Items .AddBar .AddItem("Task 1"),"Task",#1/2/2001#,#1/4/2001# .AddBar .AddItem("Task 2"),"Task",#1/5/2001#,#1/7/2001# End With End With |
593 |
How can I clip the HTML text or caption inside the bar
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Chart.Bars.Item("Task") .Pattern = exPatternBox .Height = 13 End With With .Items h = .AddItem("Task 1") .AddBar h,"Task",#1/2/2001#,#1/6/2001#,"K1","This is a bit of text that get's clipped" .ItemBar(h,"K1",exBarHAlignCaption) = 3 End With End With |
592 |
How can I align the text/caption on the scroll bar
With Gantt1 .ScrollPartCaption(exHScroll,exLowerBackPart) = "left" .ScrollPartCaptionAlignment(exHScroll,exLowerBackPart) = LeftAlignment .ScrollPartCaption(exHScroll,exUpperBackPart) = "right" .ScrollPartCaptionAlignment(exHScroll,exUpperBackPart) = RightAlignment .ColumnAutoResize = False .Columns.Add 1 .Columns.Add 2 .Columns.Add 3 .Columns.Add 4 End With |
591 |
How do I programmatically control the position of the horizontal scroll bar in the chart area, so I can specify a range of dates to scorll within
With Gantt1 .BeginUpdate .Columns.Add "Task" With .Chart .LevelCount = 2 .PaneWidth(0) = 56 .ScrollRange(exStartDate) = #1/1/2001# .ScrollRange(exEndDate) = #1/31/2001# .FirstVisibleDate = #1/12/2001# End With .ScrollPartCaption(exHChartScroll,exLowerBackPart) = .Chart.ScrollRange(exStartDate) .ScrollPartCaptionAlignment(exHChartScroll,exLowerBackPart) = LeftAlignment .ScrollPartCaption(exHChartScroll,exUpperBackPart) = .Chart.ScrollRange(exEndDate) .ScrollPartCaptionAlignment(exHChartScroll,exUpperBackPart) = RightAlignment With .Items h = .AddItem("Task 1") .AddBar h,"Task",#1/15/2001#,#1/18/2001#,"K1" h = .AddItem("Task 1") .AddBar h,"Task",#1/5/2001#,#1/11/2001#,"K1" End With .EndUpdate End With |
590 |
How can I programmatically control the position of the "splitter" between the item list on the left side and the gantt chart on the right
With Gantt1 .Chart.PaneWidth(True) = 196 End With |
589 |
How can I add a milestone bar and some text in the chart area
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h = .AddItem("Task 1") .AddBar h,"Milestone",#1/2/2001#,#1/2/2001#,,"<a1>text</a> outside" .ItemBar(h,,exBarHAlignCaption) = 18 End With End With |
588 |
How can I display or align the bar's caption or text outside of the bar
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# .DefaultItemHeight = 32 With .Items h = .AddItem("Task 1") .AddBar h,"Task",#1/3/2001#,#1/5/2001#,"K1" .ItemBar(h,"K1",exBarCaption) = "<b>to do</b>" .ItemBar(h,"K1",exBarHAlignCaption) = 18 .ItemBar(h,"K1",exBarVAlignCaption) = 16 End With End With |
587 |
How can I display or align the bar's caption or text outside of the bar
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h = .AddItem("Task 1") .AddBar h,"Task",#1/4/2001#,#1/6/2001#,"K1" .ItemBar(h,"K1",exBarCaption) = "to do" .ItemBar(h,"K1",exBarHAlignCaption) = 16 End With End With |
586 |
How can I display or align the bar's caption or text outside of the bar
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h = .AddItem("Task 1") .AddBar h,"Task",#1/2/2001#,#1/6/2001#,"K1" .ItemBar(h,"K1",exBarCaption) = "to do " .ItemBar(h,"K1",exBarHAlignCaption) = 18 End With End With |
585 |
Is there any option to count the non-working days
With Gantt1 .BeginUpdate .Chart.FirstVisibleDate = #1/1/2002# .Columns.Add "Task" With .Items h = .AddItem("Task 1") .AddBar h,"Task",#1/2/2002#,#1/4/2002#,"A" var_ItemBar = .ItemBar(h,"A",exBarNonWorkingCount) End With .EndUpdate End With |
584 |
Is there any option to count or to specify the working days
With Gantt1 .BeginUpdate .Chart.FirstVisibleDate = #1/1/2002# .Columns.Add "Task" With .Items h = .AddItem("Task 1") .AddBar h,"Task",#1/2/2002#,#1/4/2002#,"A" var_ItemBar = .ItemBar(h,"A",exBarWorkingCount) End With .EndUpdate End With |
583 |
How do I select the next row/item
With Gantt1 .Columns.Add "Column" With .Items .AddItem "Item 1" .AddItem "Item 2" .AddItem "Item 3" .SelectItem(.NextVisibleItem(.FocusItem)) = True End With End With |
582 |
How do I define the visual appearance of the bar by using your EBN/skin files
With Gantt1 .VisualAppearance.Add 1,"c:\exontrol\images\normal.ebn" .Chart.Bars.Copy("Task","EBN").Color = &H1000000 .Chart.FirstVisibleDate = #1/1/2001# .Columns.Add "Column" With .Items .AddBar .AddItem("Item 1"),"EBN",#1/2/2001#,#1/4/2001# .AddBar .AddItem("Item 2"),"Task",#1/2/2001#,#1/4/2001# End With End With |
581 |
Is it possible to have an "empty box" pattern for the bars
With Gantt1 .Chart.Bars.Copy("Task","Box").Pattern = exPatternBox .Chart.FirstVisibleDate = #1/1/2001# .Columns.Add "Column" With .Items .AddBar .AddItem("Item 1"),"Box",#1/2/2001#,#1/4/2001# .AddBar .AddItem("Item 1"),"Task",#1/2/2001#,#1/4/2001# End With End With |
580 |
How do I enable resizing ( changing the height ) the items at runtime
With Gantt1 .ItemsAllowSizing = exResizeItem .DrawGridLines = exHLines .ScrollBySingleLine = True .Columns.Add "Column" .Items.AddItem "Item 1" With .Items .ItemHeight(.AddItem("Item 2")) = 48 End With .Items.AddItem "Item 3" End With |
579 |
How do I enable resizing all the items at runtime
With Gantt1 .ItemsAllowSizing = exResizeAllItems .DrawGridLines = exHLines .Columns.Add "Column" .Items.AddItem "Item 1" With .Items .ItemHeight(.AddItem("Item 2")) = 48 End With .Items.AddItem "Item 3" End With |
578 |
I'm trying to use the percentage display in my gantt's bars. Unfortunately, I don't see any percentage on the gantt chart
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Chart.Bars.Copy("Task","BarName") .Color = RGB(255,0,0) .Pattern = exPatternBDiagonal End With .Chart.Bars.Add("BarName%Progress").Shortcut = "Percent" With .Items h = .AddItem("Task 1") .AddBar h,"Percent",#1/2/2001#,#1/6/2001#,"K1" .ItemBar(h,"K1",exBarPercent) = 0.4 .ItemBar(h,"K1",exBarShowPercentCaption) = True End With End With |
577 |
How I can show Months in Time Unit panel into Roman numerals
With Gantt1 .Chart.LevelCount = 2 .Chart.Level(0).Label = 0 With .Chart.Level(1) .Label = "<%mr%>" .Unit = exMonth End With End With |
576 |
Can I show a bar with a different vertical position
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h = .AddItem("Opaque") .AddBar h,"Task",#1/2/2001#,#1/6/2001#,"K1" h = .AddItem("Transparent and Opaque") .AddBar h,"Task",#1/2/2001#,#1/6/2001#,"K1" .ItemBar(h,"K1",exBarOffset) = "-3" .ItemBar(h,"K1",exBarTransparent) = 80 .AddBar h,"Task",#1/3/2001#,#1/7/2001#,"K2" End With End With |
575 |
How can I show transparent and opaque bars in the same chart
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h = .AddItem("Opaque") .AddBar h,"Task",#1/2/2001#,#1/6/2001#,"K1" h = .AddItem("Transparent and Opaque") .AddBar h,"Task",#1/2/2001#,#1/6/2001#,"K1" .ItemBar(h,"K1",exBarOffset) = "-3" .ItemBar(h,"K1",exBarTransparent) = 80 .AddBar h,"Task",#1/3/2001#,#1/7/2001#,"K2" End With End With |
574 |
How can I draw bars using transparent colors
With Gantt1 .Chart.ShowTransparentBars = 60 .Chart.FirstVisibleDate = #1/1/2001# .Chart.Bars.Copy("Task","TaskR").Color = RGB(255,0,0) .Chart.PaneWidth(0) = 48 .Columns.Add "Column" With .Items h = .AddItem("Item 1") .AddBar h,"Task",#1/2/2001#,#1/5/2001#,"A" .AddBar h,"TaskR",#1/4/2001#,#1/7/2001#,"B" End With End With |
573 |
Can I change the Task bar so it display a Progress or a Percent bar, but it is splitted when the task intersect a non working area
With Gantt1 With .Chart .FirstVisibleDate = #1/1/2001# .Bars.Add("Task%Progress:Split").Shortcut = "Task" End With .Columns.Add "Column" With .Items h = .AddItem("Item 1") .AddBar h,"Task",#1/2/2001#,#1/16/2001#,"K1" .ItemBar(h,"K1",exBarPercent) = 0.15 .ItemBar(h,"K1",exBarShowPercentCaption) = True End With End With |
572 |
Can I change the Task bar so it display a Progress or a Percent bar
With Gantt1 With .Chart .FirstVisibleDate = #1/1/2001# .Bars.Add("Task%Progress").Shortcut = "Task" End With .Columns.Add "Column" With .Items h = .AddItem("Item 1") .AddBar h,"Task",#1/2/2001#,#1/5/2001#,"K1" .ItemBar(h,"K1",exBarPercent) = 0.15 .ItemBar(h,"K1",exBarShowPercentCaption) = True End With End With |
571 |
How can I remove the filter
With Gantt1 With .Columns.Add("Column") .DisplayFilterButton = True .FilterType = exBlanks End With .ApplyFilter .ClearFilter End With |
570 |
I use the ShowEmptyBars property, but I display seconds from 15 to 15, and the bars are not shown correctly. What can I do
With Gantt1 .BeginUpdate With .Chart .FirstVisibleDate = #1/1/2002# .LevelCount = 2 .Level(0).Label = 1048576 With .Level(1) .Label = "<%ss%>" .Count = 15 End With .ShowEmptyBars = 15 .ShowEmptyBarsUnit = exSecond .PaneWidth(0) = 48 End With .Columns.Add "Task" With .Items h = .AddItem("Task 1") .AddBar h,"Task",#1/1/2002 0:00:15 AM#,#1/1/2002 0:00:15 AM#,"A" .AddBar h,"Task",#1/1/2002 0:01:15 AM#,#1/1/2002 0:01:30 AM#,"B" .AddLink "AB",h,"A",h,"B" End With .EndUpdate End With |
569 |
I need the bar works like in the MS Project, where task from 1/1/2001 to 1/1/2001 must display 1 day
With Gantt1 .Chart.FirstVisibleDate = #1/1/2001# .Chart.ShowEmptyBars = 1 .Columns.Add "Column" With .Items .AddBar .AddItem("Item 1"),"Task",#1/1/2001#,#1/1/2001# End With End With |
568 |
I have a bar that has the start and end date identical. Nothing is displayed. What can I do
With Gantt1 .Chart.FirstVisibleDate = #1/1/2001# .Chart.ShowEmptyBars = 1 .Columns.Add "Column" With .Items .AddBar .AddItem("Item 1"),"Task",#1/2/2001#,#1/2/2001# End With End With |
567 |
How can I display seconds and bars for 15 to 15
With Gantt1 .BeginUpdate .Chart.FirstVisibleDate = "1/1/2002 00:00" .Chart.LevelCount = 2 .Chart.Level(0).Label = 1048576 With .Chart.Level(1) .Label = "<%ss%>" .Count = 15 End With .Chart.PaneWidth(0) = 48 .Chart.Bars.Copy("Task","Task2").Color = RGB(255,0,0) .Columns.Add "Task" With .Items h = .AddItem("Task 1") .AddBar h,"Task","1/1/2002 00:00:15","1/1/2002 00:00:45","A" .AddBar h,"Task2","1/1/2002 00:01:15","1/1/2002 00:01:45","B" .AddLink "AB",h,"A",h,"B" End With .EndUpdate End With |
566 |
How can I copy a predefined bar
With Gantt1 .Chart.Bars.Copy("Task","T2").Color = RGB(255,0,0) .Chart.FirstVisibleDate = #1/1/2001# .Columns.Add "Column" With .Items .AddBar .AddItem("Item 1"),"T2",#1/2/2001#,#1/4/2001# End With End With |
565 |
How can I define my own custom bar, using my icons or pictures
With Gantt1 .Images "gBJJgBAIDAAGAAEAAQhYAf8Pf4hh0QihCJo2AEZjQAjEZFEaIEaEEaAIAkcbk0olUrlktl0vmExmUzmk1m03nE5nU7nk9n0/oFBoVDolFo1HpFJpVLplNp1PqFRqVTq" & _ "lVq1XrFZrVbrldr1fsFhsVjslls1ntFptVrtltt1vuFxuVzul1u13vF5vV7vl9v1/wGBwWDwmFw2HxGJxWLxmNx0xiFdyOTh8Tf9ZymXx+QytcyNgz8r0OblWjyWds+m" & _ "0ka1Vf1ta1+r1mos2xrG2xeZ0+a0W0qOx3GO4NV3WeyvD2XJ5XL5nN51aiw+lfSj0gkUkAEllHanHI5j/cHg8EZf7w8vl8j4f/qfEZeB09/vjLAB30+kZQAP/P5/H6/y" & _ "NAOAEAwCjMBwFAEDwJBMDwLBYAP2/8Hv8/gAGAD8LQs9w/nhDY/oygIA=" With .Chart.Bars .AddShapeCorner 12345,1 .AddShapeCorner 22345,2 With .Add("T2") .StartShape = &H5740 Or ShapeCornerEnum.exShapeIconCircleUp1 .EndShape = &H3020 Or ShapeCornerEnum.exShapeIconVBar Or ShapeCornerEnum.exShapeIconRight .EndColor = RGB(255,0,0) .Pattern = exPatternDot .Color = RGB(255,0,255) .Shape = exShapeThinCenter End With End With .Chart.FirstVisibleDate = #1/1/2001# .Columns.Add "Column" With .Items .AddBar .AddItem("Item 1"),"T2",#1/2/2001#,#1/4/2001# End With End With |
564 |
How can I access a predefined bar
With Gantt1 .Chart.FirstVisibleDate = #1/1/2001# .Columns.Add "Column" With .Items .AddBar .AddItem("Item 1"),"Task",#1/2/2001#,#1/4/2001# End With .Chart.Bars.Item("Task").Color = RGB(255,0,0) End With |
563 |
How can I access a predefined bar
With Gantt1 .Chart.FirstVisibleDate = #1/1/2001# .Columns.Add "Column" With .Items .AddBar .AddItem("Item 1"),"Task",#1/2/2001#,#1/4/2001# End With .Chart.Bars.Item("Task").Color = RGB(255,0,0) End With |
562 |
How can I remove all predefined bars
|
561 |
How can I remove a predefined bar
|
560 |
How do I get the number of predefined bars
|
559 |
How can I change the height of the task bar
With Gantt1 With .Chart.Bars.Copy("Task","T2") .Height = 24 .EndShape = exShapeIconDown1 .EndColor = RGB(255,0,0) End With .Chart.FirstVisibleDate = #1/1/2001# .Columns.Add "Column" With .Items h = .AddItem("Item 1") .ItemHeight(h) = 28 .AddBar h,"T2",#1/2/2001#,#1/4/2001# .AddBar .AddItem("Item 2"),"Task",#1/2/2001#,#1/4/2001# End With End With |
558 |
How can I change the ending shape for all task bars
With Gantt1 With .Chart.Bars.Item("Task") .EndShape = exShapeIconUp1 .EndColor = RGB(255,0,0) End With .Chart.FirstVisibleDate = #1/1/2001# .Columns.Add "Column" With .Items .AddBar .AddItem("Item 1"),"Task",#1/2/2001#,#1/4/2001# End With End With |
557 |
How can I change the height of the task bar
With Gantt1 .DefaultItemHeight = 28 .Chart.Bars.Item("Task").Height = 24 .Chart.FirstVisibleDate = #1/1/2001# .Columns.Add "Column" With .Items .AddBar .AddItem("Item 1"),"Task",#1/2/2001#,#1/4/2001# .AddBar .AddItem("Item 2"),"Task",#1/2/2001#,#1/4/2001# End With End With |
556 |
How can I change the starting shape for all task bars
With Gantt1 With .Chart.Bars.Item("Task") .StartShape = exShapeIconUp1 .StartColor = RGB(255,0,0) End With .Chart.FirstVisibleDate = #1/1/2001# .Columns.Add "Column" With .Items .AddBar .AddItem("Item 1"),"Task",#1/2/2001#,#1/4/2001# End With End With |
555 |
How can I change the height of the task bar
With Gantt1 .Chart.Bars.Copy("Task","T2").Height = 17 .Chart.FirstVisibleDate = #1/1/2001# .Columns.Add "Column" With .Items .AddBar .AddItem("Item 1"),"T2",#1/2/2001#,#1/4/2001# .AddBar .AddItem("Item 2"),"Task",#1/2/2001#,#1/4/2001# End With End With |
554 |
How can I change the height for all task bars
With Gantt1 .Chart.Bars.Item("Task").Height = 17 .Chart.FirstVisibleDate = #1/1/2001# .Columns.Add "Column" With .Items .AddBar .AddItem("Item 1"),"Task",#1/2/2001#,#1/4/2001# End With End With |
553 |
How can I change the color of the task bar
With Gantt1 .Chart.Bars.Copy("Task","T2").Color = RGB(255,0,0) .Chart.FirstVisibleDate = #1/1/2001# .Columns.Add "Column" With .Items .AddBar .AddItem("Item 1"),"T2",#1/2/2001#,#1/4/2001# .AddBar .AddItem("Item 2"),"Task",#1/2/2001#,#1/4/2001# End With End With |
552 |
How can I change the color for all task bars
With Gantt1 .Chart.Bars.Item("Task").Color = RGB(255,0,0) .Chart.FirstVisibleDate = #1/1/2001# .Columns.Add "Column" With .Items .AddBar .AddItem("Item 1"),"Task",#1/2/2001#,#1/4/2001# End With End With |
551 |
How can I change the shape for all task bars
With Gantt1 .Chart.Bars.Item("Task").Shape = exShapeSolidDown .Chart.FirstVisibleDate = #1/1/2001# .Columns.Add "Column" With .Items .AddBar .AddItem("Item 1"),"Task",#1/2/2001#,#1/4/2001# End With End With |
550 |
How can I change the shape of the task bar
With Gantt1 .Chart.Bars.Copy("Task","T2").Shape = exShapeThinCenter .Chart.FirstVisibleDate = #1/1/2001# .Columns.Add "Column" With .Items .AddBar .AddItem("Item 1"),"T2",#1/2/2001#,#1/4/2001# End With End With |
549 |
How can I change the pattern or style for all task bars
With Gantt1 .Chart.Bars.Item("Task").Pattern = exPatternFDiagonal .Chart.FirstVisibleDate = #1/1/2001# .Columns.Add "Column" With .Items .AddBar .AddItem("Item 1"),"Task",#1/2/2001#,#1/4/2001# End With End With |
548 |
How can I change the pattern of the task bar
With Gantt1 .Chart.Bars.Copy("Task","T2").Pattern = exPatternFDiagonal .Chart.FirstVisibleDate = #1/1/2001# .Columns.Add "Column" With .Items .AddBar .AddItem("Item 1"),"T2",#1/2/2001#,#1/4/2001# .AddBar .AddItem("Item 2"),"Task",#1/2/2001#,#1/4/2001# End With End With |
547 |
How can I add a percent bar in the chart area, so the task bar is splited for non working days or hours
With Gantt1 .Columns.Add "Task" .Chart.Bars.Add("Task%Progress:Split").Shortcut = "TS" .Chart.FirstVisibleDate = #1/1/2001# With .Items h = .AddItem("Task 1") .AddBar h,"TS",#1/2/2001#,#1/16/2001#,"P1" .ItemBar(h,"P1",exBarPercent) = 0.14 .ItemBar(h,"P1",exBarShowPercentCaption) = True End With End With |
546 |
How can I add a bar in the chart area, so the task bar is splited for non working days or hours
With Gantt1 .Columns.Add "Task" .Chart.Bars.Add("Task:Split").Shortcut = "TS" .Chart.FirstVisibleDate = #1/1/2001# With .Items .AddBar .AddItem("Task 1"),"TS",#1/2/2001#,#1/16/2001# End With End With |
545 |
How can I add a split bar in the chart area
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items .AddBar .AddItem("Task 1"),"Split",#1/2/2001#,#1/6/2001# End With End With |
544 |
How can I add a progress bar in the chart area
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items .AddBar .AddItem("Task 1"),"Progress",#1/2/2001#,#1/6/2001# End With End With |
543 |
How can I add a milestone bar in the chart area
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items .AddBar .AddItem("Task 1"),"Milestone",#1/2/2001#,#1/2/2001# End With End With |
542 |
How can I add a summary bar in the chart area
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items .AddBar .AddItem("Task 1"),"Summary",#1/2/2001#,#1/6/2001# End With End With |
541 |
How can I add a project summary bar in the chart area
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items .AddBar .AddItem("Task 1"),"Project Summary",#1/2/2001#,#1/6/2001# End With End With |
540 |
How can I add a deadline bar in the chart area
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items .AddBar .AddItem("Task 1"),"Deadline",#1/2/2001#,#1/2/2001# End With End With |
539 |
How can I add a task bar in the chart area
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items .AddBar .AddItem("Task 1"),"Task",#1/2/2001#,#1/4/2001# End With End With |
538 |
How can I assign a picture or an icon to a bar in the chart
With Gantt1 .HTMLPicture("p1") = "c:\exontrol\images\zipdisk.gif" .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h = .AddItem("Task 1") .ItemHeight(h) = 48 .AddBar h,"Task",#1/2/2001#,#1/6/2001#,"K1" .ItemBar(h,"K1",exBarCaption) = "<img>p1</img>" .ItemBar(h,"K1",exBarHAlignCaption) = 2 End With End With |
537 |
How can I assign a picture or an icon to a bar in the chart
With Gantt1 .Images "gBJJgBAIDAAGAAEAAQhYAf8Pf4hh0QihCJo2AEZjQAjEZFEaIEaEEaAIAkcbk0olUrlktl0vmExmUzmk1m03nE5nU7nk9n0/oFBoVDolFo1HpFJpVLplNp1PqFRqVTq" & _ "lVq1XrFZrVbrldr1fsFhsVjslls1ntFptVrtltt1vuFxuVzul1u13vF5vV7vl9v1/wGBwWDwmFw2HxGJxWLxmNx0xiFdyOTh8Tf9ZymXx+QytcyNgz8r0OblWjyWds+m" & _ "0ka1Vf1ta1+r1mos2xrG2xeZ0+a0W0qOx3GO4NV3WeyvD2XJ5XL5nN51aiw+lfSj0gkUkAEllHanHI5j/cHg8EZf7w8vl8j4f/qfEZeB09/vjLAB30+kZQAP/P5/H6/y" & _ "NAOAEAwCjMBwFAEDwJBMDwLBYAP2/8Hv8/gAGAD8LQs9w/nhDY/oygIA=" .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h = .AddItem("Task 1") .AddBar h,"Task",#1/2/2001#,#1/6/2001#,"K1" .ItemBar(h,"K1",exBarCaption) = "<img>1</img>" End With End With |
536 |
How can I display or add an anchor or a hyperlink in the link
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h1 = .AddItem("Task 1") .AddBar h1,"Task",#1/1/2001#,#1/3/2001#,"K1" .AddItem "" .AddItem "" h2 = .AddItem("Task 2") .AddBar h2,"Task",#1/5/2001#,#1/7/2001#,"K2" .AddLink "L1",h1,"K1",h2,"K2" .Link("L1",exLinkText) = "just <a1>link</a>" End With End With |
535 |
How can I display a picture or an icon on the link
With Gantt1 .Images "gBJJgBAIDAAGAAEAAQhYAf8Pf4hh0QihCJo2AEZjQAjEZFEaIEaEEaAIAkcbk0olUrlktl0vmExmUzmk1m03nE5nU7nk9n0/oFBoVDolFo1HpFJpVLplNp1PqFRqVTq" & _ "lVq1XrFZrVbrldr1fsFhsVjslls1ntFptVrtltt1vuFxuVzul1u13vF5vV7vl9v1/wGBwWDwmFw2HxGJxWLxmNx0xiFdyOTh8Tf9ZymXx+QytcyNgz8r0OblWjyWds+m" & _ "0ka1Vf1ta1+r1mos2xrG2xeZ0+a0W0qOx3GO4NV3WeyvD2XJ5XL5nN51aiw+lfSj0gkUkAEllHanHI5j/cHg8EZf7w8vl8j4f/qfEZeB09/vjLAB30+kZQAP/P5/H6/y" & _ "NAOAEAwCjMBwFAEDwJBMDwLBYAP2/8Hv8/gAGAD8LQs9w/nhDY/oygIA=" .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h1 = .AddItem("Task 1") .AddBar h1,"Task",#1/1/2001#,#1/3/2001#,"K1" .AddItem "" .AddItem "" .AddItem "" .AddItem "" h2 = .AddItem("Task 2") .AddBar h2,"Task",#1/5/2001#,#1/7/2001#,"K2" .AddLink "L1",h1,"K1",h2,"K2" .Link("L1",exLinkText) = "just <img>1</img> link" End With End With |
534 |
How can I display a picture or an icon on the link
With Gantt1 .HTMLPicture("pic1") = "c:\exontrol\images\zipdisk.gif" .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h1 = .AddItem("Task 1") .AddBar h1,"Task",#1/1/2001#,#1/3/2001#,"K1" .AddItem "" .AddItem "" .AddItem "" .AddItem "" h2 = .AddItem("Task 2") .AddBar h2,"Task",#1/5/2001#,#1/7/2001#,"K2" .AddLink "L1",h1,"K1",h2,"K2" .Link("L1",exLinkText) = "<img>pic1</img><br><br>just a link" End With End With |
533 |
How can I display some HTML text or caption on link
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h1 = .AddItem("Task 1") .AddBar h1,"Task",#1/1/2001#,#1/3/2001#,"K1" h2 = .AddItem("Task 2") .AddBar h2,"Task",#1/5/2001#,#1/7/2001#,"K2" .AddLink "L1",h1,"K1",h2,"K2" .Link("L1",exLinkText) = "L<b>1</b>" End With End With |
532 |
How can I assign a tooltip to a link
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h1 = .AddItem("Task 1") .AddBar h1,"Task",#1/1/2001#,#1/3/2001#,"K1" h2 = .AddItem("Task 2") .AddBar h2,"Task",#1/5/2001#,#1/7/2001#,"K2" .AddLink "L1",h1,"K1",h2,"K2" .Link("L1",exLinkText) = "L<b>1</b>" .Link("L1",exLinkToolTip) = "This is a bit of text that's shown when the cursor hovers the link" End With End With |
531 |
Can I change the width or the size of the link
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h1 = .AddItem("Task 1") .AddBar h1,"Task",#1/2/2001#,#1/4/2001#,"K1" h2 = .AddItem("Task 2") .AddBar h2,"Task",#1/5/2001#,#1/7/2001#,"K2" .AddLink "L1",h1,"K1",h2,"K2" .Link("L1",exLinkStyle) = 0 .Link("L1",exLinkWidth) = 2 End With End With |
530 |
Can I change the style of the link
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h1 = .AddItem("Task 1") .AddBar h1,"Task",#1/2/2001#,#1/4/2001#,"K1" h2 = .AddItem("Task 2") .AddBar h2,"Task",#1/5/2001#,#1/7/2001#,"K2" .AddLink "L1",h1,"K1",h2,"K2" .Link("L1",exLinkStyle) = 4 End With End With |
529 |
Can I change the color of the link
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h1 = .AddItem("Task 1") .AddBar h1,"Task",#1/2/2001#,#1/4/2001#,"K1" h2 = .AddItem("Task 2") .AddBar h2,"Task",#1/5/2001#,#1/7/2001#,"K2" .AddLink "L1",h1,"K1",h2,"K2" .Link("L1",exLinkColor) = 255 End With End With |
528 |
Can I change the part of the bar where the link ends
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h1 = .AddItem("Task 1") .AddBar h1,"Task",#1/2/2001#,#1/4/2001#,"K1" h2 = .AddItem("Task 2") .AddBar h2,"Task",#1/5/2001#,#1/7/2001#,"K2" .AddLink "L1",h1,"K1",h2,"K2" .Link("L1",exLinkStartPos) = 1 .Link("L1",exLinkEndPos) = 1 End With End With |
527 |
Can I change the part of the bar where the link starts
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h1 = .AddItem("Task 1") .AddBar h1,"Task",#1/2/2001#,#1/4/2001#,"K1" h2 = .AddItem("Task 2") .AddBar h2,"Task",#1/5/2001#,#1/7/2001#,"K2" .AddLink "L1",h1,"K1",h2,"K2" .Link("L1",exLinkStartPos) = 0 End With End With |
526 |
How can I associate an extra data to a link
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h1 = .AddItem("Task 1") .AddBar h1,"Task",#1/2/2001#,#1/4/2001#,"K1" h2 = .AddItem("Task 2") .AddBar h2,"Task",#1/5/2001#,#1/7/2001#,"K2" .AddLink "L1",h1,"K1",h2,"K2" .Link("L1",exLinkUserData) = "your data" End With End With |
525 |
How can I show or hide a specified link
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h1 = .AddItem("Task 1") .AddBar h1,"Task",#1/2/2001#,#1/4/2001#,"K1" h2 = .AddItem("Task 2") .AddBar h2,"Task",#1/5/2001#,#1/7/2001#,"K2" .AddLink "L1",h1,"K1",h2,"K2" .Link("L1",exLinkEndBar) = False End With End With |
524 |
How can I get the key of the bar where the link end
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h1 = .AddItem("Task 1") .AddBar h1,"Task",#1/2/2001#,#1/4/2001#,"K1" h2 = .AddItem("Task 2") .AddBar h2,"Task",#1/5/2001#,#1/7/2001#,"K2" .AddLink "L1",h1,"K1",h2,"K2" .AddItem .Link("L1",exLinkEndBar) End With End With |
523 |
How can I get the key of the bar where the link starts
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h1 = .AddItem("Task 1") .AddBar h1,"Task",#1/2/2001#,#1/4/2001#,"K1" h2 = .AddItem("Task 2") .AddBar h2,"Task",#1/5/2001#,#1/7/2001#,"K2" .AddLink "L1",h1,"K1",h2,"K2" .AddItem .Link("L1",exLinkStartBar) End With End With |
522 |
How can I get the handle of the item where the link ends
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h1 = .AddItem("Task 1") .AddBar h1,"Task",#1/2/2001#,#1/4/2001#,"K1" h2 = .AddItem("Task 2") .AddBar h2,"Task",#1/5/2001#,#1/7/2001#,"K2" .AddLink "L1",h1,"K1",h2,"K2" .AddItem .Link("L1",exLinkEndItem) End With End With |
521 |
How can I get the handle of the item where the link starts
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h1 = .AddItem("Task 1") .AddBar h1,"Task",#1/2/2001#,#1/4/2001#,"K1" h2 = .AddItem("Task 2") .AddBar h2,"Task",#1/5/2001#,#1/7/2001#,"K2" .AddLink "L1",h1,"K1",h2,"K2" .AddItem .Link("L1",exLinkStartItem) End With End With |
520 |
How can I enumerate the links in the chart
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h1 = .AddItem("Task 1") .AddBar h1,"Task",#1/2/2001#,#1/4/2001#,"K1" h2 = .AddItem("Task 2") .AddBar h2,"Task",#1/5/2001#,#1/7/2001#,"K2" .AddLink "L1",h1,"K1",h2,"K2" .AddLink "L2",h2,"K2",h1,"K1" .AddItem .FirstLink .AddItem .NextLink(.FirstLink) End With End With |
519 |
How can I access the properties and method of the link between two bars
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h1 = .AddItem("Task 1") .AddBar h1,"Task",#1/1/2001#,#1/3/2001#,"K1" h2 = .AddItem("Task 2") .AddBar h2,"Task",#1/5/2001#,#1/7/2001#,"K2" .AddLink "L1",h1,"K1",h2,"K2" .Link("L1",exLinkText) = "L<b>1</b>" End With End With |
518 |
How can I remove a link between two bars
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h1 = .AddItem("Task 1") .AddBar h1,"Task",#1/2/2001#,#1/4/2001#,"K1" h2 = .AddItem("Task 2") .AddBar h2,"Task",#1/5/2001#,#1/7/2001#,"K2" .AddLink "L1",h1,"K1",h2,"K2" .ClearLinks End With End With |
517 |
How can I remove a link between two bars
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h1 = .AddItem("Task 1") .AddBar h1,"Task",#1/2/2001#,#1/4/2001#,"K1" h2 = .AddItem("Task 2") .AddBar h2,"Task",#1/5/2001#,#1/7/2001#,"K2" .AddLink "L1",h1,"K1",h2,"K2" .RemoveLink "L1" End With End With |
516 |
How do I add a link between two bars
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h1 = .AddItem("Task 1") .AddBar h1,"Task",#1/2/2001#,#1/4/2001#,"K1" h2 = .AddItem("Task 2") .AddBar h2,"Task",#1/5/2001#,#1/7/2001#,"K2" .AddLink "L1",h1,"K1",h2,"K2" End With End With |
515 |
How do I find the number or count of bars in the item
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h = .AddItem("Task 1") .AddBar h,"Task",#1/1/2001#,#1/2/2001#,"K1" .AddBar h,"Task",#1/4/2001#,#1/6/2001#,"K2" .ItemBar(h,"K2",exBarCaption) = .ItemBar(h,,exBarsCount) End With End With |
514 |
How can I assign any extra data to a bar in the chart
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h = .AddItem("Task 1") .AddBar h,"Task",#1/2/2001#,#1/6/2001#,"K1" .ItemBar(h,"K1",exBarPattern) = "your data" End With End With |
513 |
Is there any way to change the background color for percent value being displayed on the progress bar
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# .Chart.Bars.Add("Task%Progress").Shortcut = "Percent" With .Items h = .AddItem("Task 1") .AddBar h,"Percent",#1/2/2001#,#1/6/2001#,"K1" .ItemBar(h,"K1",exBarPercent) = 0.35 .ItemBar(h,"K1",exBarShowPercentCaption) = True .ItemBar(h,"K1",exBarPercentCaptionFormat) = "<bgcolor=FF0000> %p%</bgcolor>" End With End With |
512 |
Is there any way to change the color for percent value being displayed on the progress bar
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# .Chart.Bars.Add("Task%Progress").Shortcut = "Percent" With .Items h = .AddItem("Task 1") .AddBar h,"Percent",#1/2/2001#,#1/6/2001#,"K1" .ItemBar(h,"K1",exBarPercent) = 0.35 .ItemBar(h,"K1",exBarShowPercentCaption) = True .ItemBar(h,"K1",exBarPercentCaptionFormat) = "<fgcolor=FF0000>%p%</fgcolor>" End With End With |
511 |
Is there any way to change the font for percent value being displayed on the progress bar
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# .Chart.Bars.Add("Task%Progress").Shortcut = "Percent" With .Items h = .AddItem("Task 1") .AddBar h,"Percent",#1/2/2001#,#1/6/2001#,"K1" .ItemBar(h,"K1",exBarPercent) = 0.35 .ItemBar(h,"K1",exBarShowPercentCaption) = True .ItemBar(h,"K1",exBarPercentCaptionFormat) = "<b><font Tahoma;12>%%p</font></b>" End With End With |
510 |
Is there any way to align the percent value being displayed on the progress bar
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# .Chart.Bars.Add("Task%Progress").Shortcut = "Percent" With .Items h = .AddItem("Task 1") .AddBar h,"Percent",#1/2/2001#,#1/6/2001#,"K1" .ItemBar(h,"K1",exBarPercent) = 0.75 .ItemBar(h,"K1",exBarShowPercentCaption) = True .ItemBar(h,"K1",exBarPercentCaptionFormat) = "%p/100" .ItemBar(h,"K1",exBarOffset) = 0 End With End With |
509 |
Is there any way to change the format of the percent being displayed on the progress bar
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# .Chart.Bars.Add("Task%Progress").Shortcut = "Percent" With .Items h = .AddItem("Task 1") .AddBar h,"Percent",#1/2/2001#,#1/6/2001#,"K1" .ItemBar(h,"K1",exBarPercent) = 0.4 .ItemBar(h,"K1",exBarShowPercentCaption) = True .ItemBar(h,"K1",exBarPercentCaptionFormat) = "<b>%p/100</b>" End With End With |
508 |
How can I show or hide the percent value in the progress bar
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# .Chart.Bars.Add("Task%Progress").Shortcut = "Percent" With .Items h = .AddItem("Task 1") .AddBar h,"Percent",#1/2/2001#,#1/6/2001#,"K1" .ItemBar(h,"K1",exBarPercent) = 0.4 .ItemBar(h,"K1",exBarShowPercentCaption) = True End With End With |
507 |
How can I change the percent value in a progress bar
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# .Chart.Bars.Add("Task%Progress").Shortcut = "Percent" With .Items h = .AddItem("Task 1") .AddBar h,"Percent",#1/2/2001#,#1/6/2001#,"K1" .ItemBar(h,"K1",exBarPercent) = 0.4 End With End With |
506 |
How can I add a percent bar
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# .Chart.Bars.Add "Task%Progress" With .Items h = .AddItem("Task 1") .AddBar h,"Task%Progress",#1/2/2001#,#1/6/2001#,"K1" .ItemBar(h,"K1",exBarPercent) = 0.4 End With End With |
505 |
Can I add a bar in the chart, using your EBN files
With Gantt1 .VisualAppearance.Add 1,"c:\exontrol\images\normal.ebn" .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h = .AddItem("Task 1") .AddBar h,"",#1/2/2001#,#1/5/2001#,"K1"," EBN " .ItemBar(h,"K1",exBarBackColor) = 16777216 .AddBar h,"Task",#1/6/2001#,#1/8/2001#,"K2" End With End With |
504 |
How can I change the background color of the bar in the chart
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# .Chart.Bars.Copy("Task","TaskR").Color = RGB(255,0,0) With .Items h = .AddItem("Task 1") .AddBar h,"TaskR",#1/2/2001#,#1/6/2001#,"K1" End With End With |
503 |
How can I change the background color of the bar in the chart
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h = .AddItem("Task 1") .AddBar h,"Task",#1/2/2001#,#1/6/2001#,"K1" .ItemBar(h,"K1",exBarBackColor) = 8421504 End With End With |
502 |
How can I change the background color of the HTML text or caption of the bar in the chart
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h = .AddItem("Task 1") .AddBar h,"Task",#1/2/2001#,#1/6/2001#,"K1" .ItemBar(h,"K1",exBarCaption) = "<bgcolor=FF0000> to do </bgcolor>" End With End With |
501 |
How can I change the foreground color of the HTML text or caption of the bar in the chart
With Gantt1 .Columns.Add "Task" .Chart.FirstVisibleDate = #1/1/2001# With .Items h = .AddItem("Task 1") .AddBar h,"Task",#1/2/2001#,#1/6/2001#,"K1","t<fgcolor=0000FF>o</fgcolor> do" .ItemBar(h,"K1",exBarForeColor) = 16777215 End With End With |